Oil-Immersed Power Transformers

High-capacity oil immersed power transformers for utility transmission and grid substation projects.

Request a Quote

Need Help Choosing a Product?

Tell us your voltage, capacity, and application requirements — our engineering team will recommend the right solution within 24 hours.

Technical parameters

Where power transformers sit in the network

Power transformers sit between transmission and distribution — stepping 33 kV or 66 kV down to 11 kV at an injection substation, or stepping generator output up for evacuation.

  • Injection substations — 33/11 kV and 66/11 kV, feeding a distribution ring
  • Industrial plants — captive generation step-up before parallel operation with the grid
  • Mining and heavy industry — 33 kV or 66 kV intake with high starting loads
  • Renewable evacuation — hydro, solar and wind stepping up to the collection voltage
  • Utility reinforcement — replacing or paralleling existing units

Every unit is designed to the fault level, impedance and tap range your network actually has — not a catalogue default.

What we need to size a unit

ParameterTypical rangeWhy it matters
Rated power2,500 – 31,500 kVASets core and tank size
Voltage ratio33/11 kV · 66/11 kV · 66/33 kVWinding insulation and bushings
CoolingONAN / ONAF / OFAFDetermines continuous rating
Tap changerOff-circuit (DETC) or on-load (OLTC)Voltage regulation under load
Impedance6 – 12 % typicalFault level and parallel operation
Vector groupDyn11 · YNd11 · YNyn0Parallel and protection coordination
Ambient−10 °C to +50 °CCooling design and oil expansion

If you only know kVA and voltage ratio, we will propose the rest and send the datasheet for confirmation.

Power or distribution? The difference is where it sits

Distribution transformerPower transformer
PositionEnd of the LV networkBetween transmission and distribution
Typical rating10 – 2,500 kVA2,500 – 31,500 kVA
Voltage11/0.415 kV · 33/0.415 kV33/11 kV · 66/11 kV · 66/33 kV
CoolingONANONAN / ONAF / OFAF
Tap changerUsually off-circuitOften on-load (OLTC)
ProtectionFuse or MCCBRelay, Buchholz, differential

If your unit steps down to 415 V, you need a distribution transformer. If it steps 33 kV or 66 kV down to 11 kV for onward distribution, it is a power transformer.

Supplied as a substation, not just a transformer

Most power transformers leave our works as part of a package: transformer, MV switchgear, protection and control panel, and LV distribution — factory-assembled and tested where a compact substation is specified.

This shortens site work and puts one party responsible for the interface.

Frequently asked

What is the largest unit you manufacture?

Up to 31,500 kVA at 38 kV maximum system voltage. Above that we quote in coordination with a partner works and supply under our project management.

Do you supply on-load tap changers?

Yes. OLTC units are available with automatic voltage control, and we specify the tap range against your actual incoming voltage profile rather than a default ±8 × 1.25 %.

Can you match an existing transformer for parallel operation?

Yes, provided we know the existing vector group, impedance and tap range. We ask for the nameplate photo and match impedance within the tolerance needed for parallel running.

What testing is done before shipment?

Routine tests to IEC 60076-1 on every unit: winding resistance, ratio, impedance and load loss, no-load loss and current, applied and induced voltage, plus oil tests. Type test reports from the same design family are supplied on request.