Oil-Immersed Power Transformers
High-capacity oil immersed power transformers for utility transmission and grid substation projects.

Need Help Choosing a Product?
Tell us your voltage, capacity, and application requirements — our engineering team will recommend the right solution within 24 hours.
Where power transformers sit in the network
Power transformers sit between transmission and distribution — stepping 33 kV or 66 kV down to 11 kV at an injection substation, or stepping generator output up for evacuation.
- Injection substations — 33/11 kV and 66/11 kV, feeding a distribution ring
- Industrial plants — captive generation step-up before parallel operation with the grid
- Mining and heavy industry — 33 kV or 66 kV intake with high starting loads
- Renewable evacuation — hydro, solar and wind stepping up to the collection voltage
- Utility reinforcement — replacing or paralleling existing units
Every unit is designed to the fault level, impedance and tap range your network actually has — not a catalogue default.
What we need to size a unit
| Parameter | Typical range | Why it matters |
|---|---|---|
| Rated power | 2,500 – 31,500 kVA | Sets core and tank size |
| Voltage ratio | 33/11 kV · 66/11 kV · 66/33 kV | Winding insulation and bushings |
| Cooling | ONAN / ONAF / OFAF | Determines continuous rating |
| Tap changer | Off-circuit (DETC) or on-load (OLTC) | Voltage regulation under load |
| Impedance | 6 – 12 % typical | Fault level and parallel operation |
| Vector group | Dyn11 · YNd11 · YNyn0 | Parallel and protection coordination |
| Ambient | −10 °C to +50 °C | Cooling design and oil expansion |
If you only know kVA and voltage ratio, we will propose the rest and send the datasheet for confirmation.
Power or distribution? The difference is where it sits
| Distribution transformer | Power transformer | |
|---|---|---|
| Position | End of the LV network | Between transmission and distribution |
| Typical rating | 10 – 2,500 kVA | 2,500 – 31,500 kVA |
| Voltage | 11/0.415 kV · 33/0.415 kV | 33/11 kV · 66/11 kV · 66/33 kV |
| Cooling | ONAN | ONAN / ONAF / OFAF |
| Tap changer | Usually off-circuit | Often on-load (OLTC) |
| Protection | Fuse or MCCB | Relay, Buchholz, differential |
If your unit steps down to 415 V, you need a distribution transformer. If it steps 33 kV or 66 kV down to 11 kV for onward distribution, it is a power transformer.
Supplied as a substation, not just a transformer
Most power transformers leave our works as part of a package: transformer, MV switchgear, protection and control panel, and LV distribution — factory-assembled and tested where a compact substation is specified.
This shortens site work and puts one party responsible for the interface.
Frequently asked
What is the largest unit you manufacture?
Up to 31,500 kVA at 38 kV maximum system voltage. Above that we quote in coordination with a partner works and supply under our project management.
Do you supply on-load tap changers?
Yes. OLTC units are available with automatic voltage control, and we specify the tap range against your actual incoming voltage profile rather than a default ±8 × 1.25 %.
Can you match an existing transformer for parallel operation?
Yes, provided we know the existing vector group, impedance and tap range. We ask for the nameplate photo and match impedance within the tolerance needed for parallel running.
What testing is done before shipment?
Routine tests to IEC 60076-1 on every unit: winding resistance, ratio, impedance and load loss, no-load loss and current, applied and induced voltage, plus oil tests. Type test reports from the same design family are supplied on request.