YINMA Electric · Taizhou, Zhejiang

2×1000 kVA Box Substations + Charging Piles
YINMA Equipment and Installation Guidance for a Building-Materials Park

YINMA supplied two 1000 kVA-class box substations and guided the interface to the charging equipment. The contractor built two foundations and cable wells, and carried out the trenchless cable route.

2×1000
kVA Box Substations
2
Foundations & Cable Wells
Trenchless
Cable Route
Charging
Pile Interface
1000 kVA-class box substation open for inspection at a Taizhou building-materials park

Two Box Substations, One Charging Demand

A building-materials park needed power for a charging area. The scheme uses two 1000 kVA-class box substations, two foundations and two cable wells, with a trenchless cable route.

The site is a building-materials park in Taizhou. Charging demand is being added in phases, so the project uses two 1000 kVA-class box substations rather than one large unit: loads can be split between the two, a fault in one does not take out the whole charging area, and future piles can be added to the substation with spare capacity.

The two substations sit on separate concrete foundations, each with a cable well. The cable route is trenchless, avoiding a long open cut across the park. YINMA supplied the two box substations and guided the equipment-side installation; foundations, wells, trenchless work and cable laying were carried out by the contractor.

Who Did What

Equipment and installation guidance from YINMA; civil works, foundations, cable wells and trenchless cable route from the contractor.

ScopeYINMA ElectricContractor
EquipmentTwo 1000 kVA-class box substations—
InstallationGuidance: foundation checks, cable entry, earthing, ventilation, pre-energizationFoundations, cable wells, trenchless route, cable laying
Charging interfaceGuidance on LV feeder and protection interface to the charging equipmentCharging pile installation and connection

YINMA's role is to make sure the two box substations are landed, connected and checked correctly before they feed the charging area.

Six Checks for a Two-Substation Charging Project

Points checked on site before the charging area was energised.

📏

Two Foundations, One Level

Check elevation, flatness and embedded parts on both foundations. A height difference makes cable termination and future maintenance harder.

💧

Drainage and Cable Wells

Cable wells must drain and align with the substation cable entry. Standing water is the most common long-term problem in outdoor charging sites.

🛢️

Trenchless Cable Entry

Check bend radius, pulling tension and sealing at the duct entry. Cable damage during pulling may only show up months later.

🌡️

Ventilation and Clearance

Keep the ventilation path clear and leave enough space for door opening and maintenance on both substations.

⚡

Earthing and Neutral

Check enclosure earthing, neutral earthing and cable shield bonding. Charging loads are sensitive to poor earthing.

✅

Before Energization

Insulation, phase sequence, protection settings and interlock checks before the first charging session.

From Foundations to Charging Cabinets

Photos follow the site sequence: cable trench, foundations, cabinet placement, cable termination and charging equipment.

Site works with overhead connection and cable pulling
Site works: overhead connection and cable pulling near the building.
YINMA YBP-10/0.4-1000 box substation nameplate
YINMA YBP-10/0.4-1000 nameplate: 1000 kVA capacity, September 2026 factory date.
Metering and LV wiring inside the box substation
Metering and LV wiring checked inside the box substation.
GGD low-voltage incoming cabinet
GGD low-voltage incoming cabinet; breaker and indication checked.
DC fast charger on a concrete base
DC fast charger installed on its concrete base.
Boom lift and cable work at the site
Boom lift working near the building; external line and cable connection.

What African Industrial and Logistics Parks Can Reuse

Phased charging demand, limited road access and hot, dusty sites are common in African industrial parks.

1. Phased Charging Loads

Start with a few chargers and add later. Two 1000 kVA-class substations let the park split the load and expand without replacing the whole power centre.

2. No Long Road Cuts

Trenchless cable routes reduce disruption in operating industrial parks. The cable wells and duct entries must be planned with the substation foundations.

3. Heat, Dust and Drainage

Outdoor charging cabinets need clear ventilation, filtered air paths and foundations that drain. In African rainy seasons, a poorly drained cable well becomes a fault point.

For African EPCs and park developers, the practical lesson is to design the charging area as a power project — foundations, cable route, earthing and protection — not as a set of standalone chargers.

Box Substations and Charging Interfaces

YINMA supports industrial parks, logistics hubs and charging areas with box substations and equipment-side guidance.

    • Two 1000 kVA-class box substations, supplied as a package;
    • Load-split advice for two-substation charging areas;
    • Guidance on foundation, cable entry and cable-well interfaces;
    • Pre-energization checks with the contractor and charging operator.

YINMA supplies the box substations and guides installation. Foundations, cable wells, trenchless work and cable laying remain with the contractor.

For box substation options, see compact substations. For load and configuration, see the transformer selection guide. To discuss a charging-area design, contact YINMA. For an 11-charger heavy truck site, see the Yueqing charger case.

Common Questions

Q: Do the two 1000 kVA substations have to be paralleled?
A: Not necessarily. They can run separately or with a bus-tie, depending on load priority and metering. Decide the load split first, then the operating mode.

Q: Why does each box substation need a cable well?
A: For cable entry, inspection and drainage. The well should align with the duct and the substation cable entry so the cable does not bend sharply.

Q: Does YINMA build the foundations or the trenchless route?
A: No. YINMA supplies the box substations and guides installation; foundations, wells, trenchless work and cable laying are carried out by the contractor.

Charging Areas Need a Power Design, Not Just Chargers
YINMA Box Substations for Industrial Parks

From a single box substation to a two-substation charging area, YINMA supports industrial parks and logistics hubs with equipment and installation guidance. Send us your load list and site plan.

Pour aller plus loin

Xu Jianye chez Yinma Electric, Yueqing — fondateur, ouvrier de ligne, inspecteur qualité
Actualités

Jianye Xu, fabricant de transformateurs

Jianye Xu a fondé Yinma Electric à Yueqing. Il reste à l'atelier, arrête une expédition non conforme et vient de Chine si le chantier l'exige.

Lire l'article →
57 unités d'appareillage électrique GGD LV dans le cadre du projet industriel de Jinghesheng : étude de cas
Actualités du secteur

57 GGD LV Appareillages de commutation : la fiabilité de la distribution industrielle, de Songzi à l'Afrique

Yinma Electric a fourni 57 appareillages de commutation basse tension GGD au projet industriel de Jinghesheng à Songzi — une solution de distribution industrielle qui a fait ses preuves dans les mines, les usines et les parcs industriels africains.

Lire l'article →
Ligne aérienne 11 portées + transformateur sur poteau 250 kVA : YINMA au Zhejiang
Actualités du secteur

Ligne 11 portées + transfo sur poteau 250 kVA | YINMA

YINMA a fourni un transformateur sur poteau 250 kVA et un coffret JP pour un parc agricole ; l'entrepreneur a réalisé les poteaux et la ligne.