Hubei Jinghesheng Biotechnology · Songzi Port Industrial Park · Phase II commissioned this year, with no equipment faults found in our follow-up visits.

A 17,000 t/y Pesticide Project Enters Operation
Hubei Jinghesheng Biotechnology's 17,000 t/y pesticide technical and intermediate project is located in Songzi Port Industrial Park, Jingzhou, Hubei. The project represents a total investment of RMB 120 million, including RMB 15.72 million for environmental protection.
| Item | Details |
|---|---|
| Project | 17,000 t/y pesticide technical & intermediate project |
| Owner | Hubei Jinghesheng Biotechnology Co., Ltd. |
| Nature | Expansion within the existing plant |
| Location | No. 9 Fenglin Avenue, Songzi Port Industrial Park, Jingzhou, Hubei |
| Investment | RMB 120 million, including RMB 15.72 million for environmental protection |
| Scope | 5 production lines, 2 Class A warehouses, 2 Class C warehouses and supporting environmental facilities |
| Status | Commissioned this year |
Yinma Electric took part in the electrical distribution works across both phases: transformers and substation equipment for Phase I, and 57 GGD AC low-voltage distribution panels for Phase II.
Two Phases, Two Different Equipment Packages
Phase I and Phase II were built at different times, with different distribution requirements. Yinma Electric supplied equipment for both.
| Phase | Yinma Electric Scope | Role |
|---|---|---|
| Phase I | Transformers and substation equipment | HV-to-LV power supply for the existing plant |
| Phase II | 57 GGD AC low-voltage distribution panels | Incoming, capacitor compensation, bus-tie, LV feeders and motor control |
The Phase I equipment was commissioned earlier. Our service team visits the site regularly for follow-up checks; to date, no faults have been found in the equipment we supplied.
For Phase II, the 57 GGD panels cover incoming panels, capacitor compensation panels, bus-tie panels, low-voltage feeder panels and motor control panels. They carry power from the transformer LV side to production equipment, lighting and auxiliary systems across the plant.
57 GGD Panels: Standard, Robust, Maintainable
GGD is a mature low-voltage distribution platform: simple construction, universal components and straightforward maintenance. The configuration below was used for the Jinghesheng Phase II project.
| Parameter | Project Configuration |
|---|---|
| Rated operating voltage | AC 380 V / 400 V |
| Rated frequency | 50 Hz |
| Rated current | 630 A – 3200 A |
| Rated short-time withstand current | 30 kA / 1 s |
| Rated peak withstand current | 63 kA / 0.1 s |
| Protection degree | IP30 (IP40 / IP54 optional) |
| Busbar rated current | Up to 3200 A, pure copper, tin-plated joints |
| Standards | IEC 61439-1/2, GB/T 7251.1 |
| Enclosure | 2.0 mm cold-rolled steel, electrostatic powder coating |
| Design life | ≥20 years |
Six Design Choices Made for the Plant Floor
Each item below addresses a real failure mode in continuous-process plants, not a catalogue feature.
Standard Modular Construction
Standard modules and market-available breakers, contactors and meters. Replacement parts do not require new tooling, and local electricians can carry out maintenance.
Five-Protection Interlocking
Mechanical interlocking prevents opening or closing disconnectors under load, entering live compartments, incorrect breaker operation, energizing with the earth switch closed, and closing with earth connected.
Low Temperature-Rise Busbars
Large-section copper busbars, tin-plated joints and top/bottom ventilation keep the panel stable at full load in 40–45°C ambient conditions.
Chemical-Plant Corrosion Protection
Acid pickling, phosphating and epoxy powder coating; optional salt-spray, anti-fungal and moisture-proof finish for chemical, mining and coastal environments.
Capacitor Compensation
Capacitor compensation panels are installed and switched according to load. Long-term power factor data was not recorded, so this article does not quote a power-factor figure.
Reserved Expansion Capacity
Busbar positions and enclosure space are reserved for future circuits. Adding a production line requires new switch units, not a complete panel replacement.
25 Days to Build, 7 Days to Commission
The Phase II package was delivered against the site energization schedule, not against a generic factory lead time.
The 57 panels were produced in 25 days, shipped in batches against the site schedule, and installed, wired, protection-set and energized within 7 days. All 57 panels energized successfully on the first attempt.
Phase II entered formal operation this year. Our service team visits the site regularly; no faults have been found in the Phase I transformers and substation equipment or the Phase II GGD panels.
Why This Project Matters for African Plants
Songzi is a continuous-process chemical plant with corrosive atmosphere, heavy motor loads and phased expansion — the same conditions found in African pesticide, fertiliser, chemical and mining projects.
1. Pesticide, Fertiliser & Chemical Plants
Continuous process, corrosive gases and dust demand panels that resist corrosion and can be maintained locally. GGD's standard components and optional anti-corrosion finish fit this environment.
2. Mining & Mineral Processing
Crushing, grinding, flotation and pump stations carry heavy motor loads and high dust. GGD's breaking capacity and IP54 option suit these sites.
3. Industrial Parks & Special Economic Zones
Phased construction needs standardised LV switchgear that can be extended tenant by tenant. GGD's modular design supports that model.
4. Food, Timber & Building Materials
Motor-heavy workshops in humid, dusty conditions need robust motor control and simple spare parts. GGD MCC sections are a practical fit.
5. Solar & Storage LV Side
Station service and LV grid-connection distribution can be configured with protection for inverters and PCS units.
For African projects, the value of GGD is not a headline specification — it is standard components, fast delivery and the ability to add circuits later without replacing the whole panel.
From Load List to Commissioning
We supply the panels and the engineering behind them: drawings, factory testing, export packing, site guidance and follow-up visits.
Distribution Design
Single-line diagrams and panel layouts based on the load list, site environment and grid conditions.
Factory Assembly & Testing
Panels assembled, wired, dielectric-tested and protection-set at our Wenzhou factory before shipment.
Export Packing
Fumigated wooden crates with moisture-proof and shock-absorbing inner packing for sea and inland transport.
Site Guidance
Engineers can attend site for installation, commissioning and operator training; remote video guidance is also available.
Spares & Warranty
Common breaker and contactor spares, two-year whole-unit warranty and lifetime technical support.
Certification Support
CCC, CE and IEC documentation; support for SONCAP, PVOC and SABS import requirements.
Reliable LV Distribution for Continuous Production
Yinma GGD Switchgear for African Plants
From a single panel to a full 57-panel package, we configure GGD switchgear for voltage, protection degree and circuit schedule. African EPCs, plant owners and electrical contractors are welcome to request drawings and a quotation.