Jinghesheng Phase II: 57 GGD Panels for a Pesticide Plant

Localização
Songzi, Hubei, China
Indústria
Industrial
Concluído
2026
Escala do Projeto
57 GGD panels

57 GGD panels, 25-day production and 7-day commissioning for a continuous-process pesticide plant

Histórico e desafios do projeto

Requisitos do cliente

The Jinghesheng Phase II expansion needed 57 GGD low-voltage panels for five new production lines, two Class A and two Class C warehouses, with spare circuits for future expansion. Yinma Electric had already supplied transformers and substation equipment for Phase I.

Principais problemas de fonte de alimentação

  • Corrosive chemical atmosphere and dust accelerated corrosion on previous panel finishes.
  • Continuous-process loads and large motors required high short-circuit withstand and reliable motor control.
  • The expansion had to be energised against a tight site schedule, not a generic factory lead time.
  • Future production lines required reserved busbar and feeder capacity without replacing whole panels.

A nossa solução

Yinma Electric supplied 57 GGD AC low-voltage panels covering incoming, capacitor compensation, bus-tie, LV feeders and motor control. Panels were produced in 25 days, installed and commissioned in 7 days, and energised successfully on the first attempt.

Lista de produtos fornecidos

Notas de personalização

IEC 61439-1/2 design, IP30 enclosure with anti-corrosion finish, reserved busbar capacity for future lines, and English-Chinese circuit schedules for handover.

Resultados e valor do projeto

57GGD Panels (Phase II)
25 daysProduction
7 daysCommissioning
0Faults Found in Follow-ups

"Our service team visits the site regularly; to date no faults have been found in the equipment supplied for either phase."

Yinma Electric Service TeamJinghesheng follow-up visits

Produtos Utilizados neste Projeto

Equipamento principal fornecido para este projeto de transformador Nigeria industrial.

Solicite uma solução semelhante

Planeamento de um projeto de transformador Industrial em Nigeria? Os nossos engenheiros irão conceber um pacote personalizado com base nesta implementação de referência comprovada.

Parâmetros técnicos